Monday, December 20, 2010

Reserva Completion Schedule

Here is an updated construction calendar for Costa Reserva.
ID
TASK
LENGTH
BEGINING
ENDING
 PREDECESSOR
1
Start Order
0 days
Mon 01/17/11
Mon 01/17/12

2
Phase 1 (easements  1,4,5)
65 days
Mon 01/17/12
Fri 04/15/11

3
Electric System design and permits
35 days
Mon 01/17/11
Fri 03/04/11
1
4
Electric System Construction
20 days
Mon 03/07/11
Fri 04/01/11
3
5
Tests and running of Electric System
10 days
Mon 04/04/11
Fri 04/15/11
4
6
Water Tank Construction
30 days
Mon 01/17/11
Fri 02/25/11
1
7
Pumping Tank Construction (Esterillos)
20 days
Mon 02/28/11
Fri 03/25/11
6
8
Pumping System
20 days
Fri 03/04/11
Thu 03/31/11
7 FC- 16 days
9
Tests and running of potable water
10 days
Fri 04/01/11
Th 04/14/11
8
10
Delivery phase 1
0 days
Mon 01/17/18
Fri 04/15/11
5,9
11
Phase 2 (6,12,14,17,19,3,13)
30 days
Mon 04/04/11
Fri 05/13/11

12
Electric System Construction
20 days
Mon 04/04/11
Fri 04/29/11
4
13
Tests and running of Electric System
10 days
Mon 05/02/11
Fri 05/13/11
12
14
Tests and running of potable water
10 days
Fri 04/15/11
Th 04/28/11
9
15
Delivery phase 2
0 days
Fri 05/13/11
Th 05/13/11
14,13
16
Phase 3 (2, 24, 25)
50 days
Mon 04/18/11
Fri 06/24/11

17
Base and cobblestone placing
40 days
Mon 04/18/11
Fri 06/10/11
10
18
Electric System Construction
20 days
Mon 05/16/11
Fri/06/10/11
12, 17 FC- 20 days
19
Tests and running of Electric System
10 days
Mon 06/13/11
Fri 06/24/10
18
20
Tests and running of potable water
10 days
Mon 05/30/11
Fri/06/10/11
17 FC-10 days, 14
21
Delivery phase 3
0 days
Fri 06/24/11
Fri 06/24/11
20, 19
22
Phase 4 (20,21,22,23)
70 days
Mon 05/16/11
Fri 08/19/11

23
Sub-base placing and pipes construction
30 days
Mon 05/16/11
Fri 06/24/11
15
24
Base and cobblestone placing
40 days
Mon 06/13/11
Fri 08/05/11
23 FC-20 days 17
25
Electric System Construction
20 days
Mon 07/11/11
Fri 08/05/11
24 FC-20 days
26
Tests and running of Electric System
10 days
Mon 08/08/11
Fri 08/19/11
25
27
Tests and running of potable water
10 days 
Mon 07/25/11
Fri 08/05/11
24 FC- 10 days
28
Delivery phase 4
0 days
Fri 08/19/11
Fri 08/19/11
26, 27
29
Phase 5 (7,8,9,10,11)
80 days
Mon 06/27/11
Fri 10/14/11

30
Sub-base placing and pipes construction
30 days
Mon 06/27/11
Fri 08/05/11
23
31
Base and cobblestone placing
40 days
Mon 08/05/11
Fri 09/30/11
30FC-20 days, 24
32
Electric System Construction
20 days
Mon 09/05/11
Fri 09/30/11
31 FC- 20 days
33
Tests and running of Electric System
10 days
Mon 10/03/11
Fri 10/14/11
32
34
Tests and running of potable water
10 days 
Mon 09/19/11
Fri 09/30/11
31 Fc-10 days
35
Delivery phase 5
0 days
Fri 10/14/ 11
Fri 10/14/11
33,34
36
Phase 6 (15,16,18,26)
180 days
Mon 04/04/11
Fri 12/09/11

37
Earth movements
40 days
Mon 04/04/11
Fri 05/27/11

38
Mechanic piping installation
20 days
Mon 05/30/11
Fri 06/24/11
37
39
Sub-base placing and pipes construction
30 days
Mon 08/08/11
Fri 09/16/11
38,30
40
Base and cobblestone placing
40 days
Mon 10/03/11
Fri 11/25/11
39 FC- 20 days, 31
41
Electric System Construction
20 days
Mon 10/31/11
Fri 11/25/11
40 FC-20 days
42
Tests and running of Electric System
10 days
Mon 11/28/11
Fri 12/09/11
41
43
Tests and running of potable water
10 days 
Mon 11/14/11
Fri 11/25/11
40 FC-10days
44
Delivery phase 6
0 days
Fri 12/09/11
Fri 12/09/12
43,43
45
Project Delivery
0 days
Fri 12/09/11
Fri 12/09/12
10,15,21,28,35,44,